Building & Construction Industry Security Of Payments Act 1999

Including amendments to 20 August 2024 and the Building & Construction Industry Security of Payment Regulation 2020. The rules below apply to construction contracts entered into on or after 21 October 2019 (older contracts are governed by the Act as it stood when the contract was made).

Who can claim:

The Act applies to any construction contract for construction work or related goods and services in NSW, whether written, oral or partly both (section 7). Since 1 March 2021 it also applies to residential building work for an owner-occupier. However, since 20 August 2024 there is no entitlement to a progress payment if the contract does not comply with section 4 of the Home Building Act 1989, or the residential building work was carried out without the licence or insurance required by section 92 of that Act (section 8(2)). A company in liquidation cannot serve a payment claim or apply for adjudication (section 32B).

Making A Claim Under The Security Of Payments Act NSW

For a payment claim to be valid and effective under the Security Of Payments Act NSW the following details must be included, correct and complete:

Construction Contract

There must be a construction contract within the meaning of the Security Of Payment Act NSW in place between the parties to a claim. If the contract has been terminated, a payment claim may still be served on and from the date of termination (section 13(1C)).

The claim must say it is made under the Act:

A payment claim must state that it is made under the Building and Construction Industry Security of Payment Act 1999 (NSW) (section 13(2)(c)). An invoice without this statement is not a payment claim under the Act and will not support an adjudication application. This is the most common reason claims fail.

Time For Making A Claim:

You may serve one payment claim per named month, on and from the last day of the month in which the work was carried out (or an earlier date if the contract allows one) (section 13(1A)-(1B), (5)). A single claim may cover more than one progress payment and may include amounts claimed previously but still unpaid (section 13(6)). A claim must be served within the period allowed by the contract or within 12 months after the work was last carried out (or goods and services last supplied), whichever is later (section 13(4)).

Entity Details:

Both of the entities details that have contracted must be complete and correct inclusive of ABN & ACN numbers

Project Details:

Name of the project if there is one and or a brief description of the project and the project site address.

Identifying the construction work:

As briefly as possible but correctly and comprehensively itemise the work, goods or services for which you are claiming payment for (section 13(2)(a)).

Calculating the Amount:

It will either be as set out in the contract, or, if it is not set out in the contract you must show how you have calculated the total amount claimed (sections 9, 10 and 13(2)(b)). The claim may include retention money you say is due for release (section 13(3)).

Due Date For Payment (section 11):

(a) A progress payment from a principal to a head contractor is due 15 business days after the payment claim is made, or earlier if the contract provides an earlier date.

(b) A progress payment to a subcontractor is due 20 business days after the payment claim is made, or earlier if the contract provides an earlier date.

(c) A progress payment under an owner-occupier residential contract is due on the date the contract provides, or if the contract is silent, 10 business days after the payment claim is made.

A contract term that provides a longer period has no effect. Interest runs on unpaid amounts from the due date at the Civil Procedure Act 2005 rate or the contract rate, whichever is greater.

Supporting Statement (head contractors only):

A head contractor must not serve a payment claim on the principal unless it is accompanied by a supporting statement in the approved form declaring that all subcontractors it directly engaged have been paid what is due to them (section 13(7); Regulation clause 18). Maximum penalty 1,000 penalty units (currently $110,000) for a corporation or 200 penalty units ($22,000) for an individual. Knowingly serving a false or misleading supporting statement carries the same penalty and, for an individual, up to 3 months imprisonment (section 13(8)). A supporting statement is not required for claims by subcontractors or for claims served directly on an owner-occupier.

Serving the Claim (section 31):

Any document that by or under the Security Of Payments Act NSW is authorised or required to be served on a person may be served on the person:

(a) by delivering it to the person personally, or

(b) by lodging it during normal office hours at the person’s ordinary place of business, or

(c) by sending it by post addressed to the person’s ordinary place of business, or

(d) by email to an email address the person has specified for the service of documents of that kind, or

(e) in such other manner as may be authorised by the regulations, or

(f) in such other manner as may be provided under the construction contract concerned.

Service of a document sent by post to a person’s ordinary place of business is taken to have been effected when the document is received at that place. These provisions are in addition to, and do not limit, any other law with respect to the service of documents.

What happens next:

The respondent has 10 business days after the claim is served to reply with a payment schedule (section 14). If no schedule is served, the full claimed amount becomes a debt due on the due date, and you may then serve a notice of your intention to apply for adjudication – that notice must be served within 20 business days after the due date (section 17(2)). See Applying for Adjudication.

A sample Security Of Payments Act NSW Payment Claim form can be found here.